How to Specify a Floor Access Door: Size, Load, Finish and Fire Rating

A step-by-step specification for a commercial floor hatch: size, load, lid type, finish, drainage, operation, locking and fire evidence.

A floor access door, also called a floor hatch or floor door, is a hinged or lift-out cover set into a floor slab to give access to a pit, vault, plant space or service run below. To specify one, settle six things: the opening size, the load the lid must carry, the lid type and finish, whether water will reach it, how it opens and locks, and whether it sits in a fire-rated floor. OSHA’s general industry rule for covers over holes in walking-working surfaces is 29 CFR 1910.29(e): the cover must support at least twice the maximum intended load and be secured against accidental displacement.

This guide follows a floor door schedule line by line, for commercial, institutional and industrial buildings, using the figures Surespan’s data sheets print. For a plain definition first, see What is a Floor Door?

Which type of floor access door fits the job?

Start with the lid, because it decides most of what follows. Surespan makes five types, each with its own data sheet:

Type
Model
What the data sheet states
HIAC
Recessed lid that can take a recess of up to 100mm (3.9 in) for infill; standard material aluminum, stainless steel grade 304 or grade 316, depending on size.
SAC
Lid flush with the floor in aluminum 5 bar tread plate, plain plate also available; not watertight, self-draining.
EHDC
Cast aluminum magnesium alloy, cover of aluminum checker plate, foldaway hinges; not watertight, self-draining.
RSI
Aluminum cover and frame on an upstand, single or double leaf, designed to prevent the ingress of rainwater, animals and insects.
IAC
Aluminum checker plate lid for pedestrian areas; the drawing shows horizontal and vertical installation.

How big is the opening, and how big is the frame?

Size a floor door from the structural opening, the rough opening in the slab. The frame is always larger, and the sheets state by how much:

  • HIAC: overall dimension SO + 250 mm (9.8 in), frame on the hinge side SO + 150 mm (5.9 in);
  • SAC: overall frame SO + 329 mm (13.0 in);
  • EHDC: overall frame SO + 370 mm (14.6 in);
  • RSI: overall frame SO + 206 mm (8.1 in);
  • IAC: overall frame SO + 44 mm (1.7 in), with 5mm (0.2 in) clearance allowed in the structural opening.

The HIAC, SAC, RSI and IAC are custom made to any size. The RSI and EHDC also come in standard sizes, for example the RSI/60.60 at 600 x 600 mm (23.6 x 23.6 in) and 34kg (approx. 75 lb), up to the RSI/150.150 at 1500 x 1500 mm (59.1 x 59.1 in) and 111kg (approx. 245 lb), and the EHDC/60.60 at 600 x 600 mm (23.6 x 23.6 in) and 65kg (approx. 143 lb), up to the EHDC/90.180 at 900 x 1800 mm (35.4 x 70.9 in) and 186kg (approx. 410 lb). Put the weight on the schedule: it matters for handling, hinges and the operating method.

What load does the floor door need to carry?

OSHA sets a minimum for any cover over a hole in a walking-working surface. Under 29 CFR 1910.29(e), the employer must ensure each cover “is capable of supporting without failure, at least twice the maximum intended load that may be imposed on the cover at any one time” and “is secured to prevent accidental displacement.” The maximum intended load is yours to define, so write it down: foot traffic, carts, pallet trucks, vehicles, or equipment set down on the lid.

Surespan’s sheets give two kinds of load. Pedestrian loads are spread over an area, in kN/m²; vehicle loads are given per wheel, in kN:

Use, as the sheet describes it
Load printed on the sheet
Pedestrian light
2.5 kN/m² (approx. 52 psf)
Pedestrian medium
5 kN/m² (approx. 104 psf)
Pedestrian heavy
10 kN/m² (approx. 209 psf)
Car light
W3, 15 kN wheel load
Car medium
W4, 25 kN wheel load
Car heavy
W5, 50 kN wheel load
Van heavy
W6, 65 kN wheel load
Heavy goods vehicle
W7, 108 kN wheel load
Heaviest class on the sheet
W8, 158 kN wheel load

The full table appears on the HIAC, SAC and EHDC sheets. The RSI is rated at 2.5 or 5kN/m2 loading, and the IAC is a pedestrian door. An area load and a wheel load are not interchangeable: a door good for 10 kN/m² of foot traffic is not thereby good for a pallet truck. Many US schedules ask for an H-20 rating. H-20 is a highway bridge design vehicle, not a floor door class. No Surespan sheet uses it, and none of the figures above should be read as equal to it. Give the structural engineer the real wheel loads, contact areas and route, and let the engineer confirm the selection.

Which lid and finish should you choose?

  • Recessed lid (HIAC) where the floor finish must run across the door. The sheet says the lid is recessed to accommodate any type of infill. Heavier infill adds dead load, and the sheet ties the operating method to “loading, infill and size”, so give the infill material and depth at enquiry stage.
  • Checker plate or plain plate on the SAC, EHDC, RSI and IAC, where an exposed metal lid is acceptable.
  • Slip resistance: an anti-slip coating is available on the plate lids, and every one of the five sheets lists the SureGrip non slip finish.
  • Material: the HIAC and SAC sheets list stainless steel grade 304 or 316, aluminum and galvanized steel as options; the RSI uses marine grade aluminum as standard.

Will water reach the door?

For exterior slabs, podiums and wash-down areas, decide early whether the door must keep water out or drain it away. The SAC and EHDC sheets are explicit: “This access cover is not watertight, it is ‘self-draining’.” Each has an integral drainage channel fitted as standard with an external ¾ inch flexible hose adaptor, for connection to drain by others. The SAC sheet adds that external drainage is possible if required.

That is the honest limit of a flush, self-draining door. If the space below must stay dry, it is the wrong choice unless the drain connection is designed and installed. The RSI, which sits on an upstand, is designed to prevent the ingress of rainwater, animals and insects, and its insulation is rated 0.43 W/m²K. That figure is the U-value of the insulation, not of the whole door.

How should it open and lock?

The HIAC, SAC and EHDC sheets use the same rule: gas spring assisted opening on smaller sizes, with larger doors electric or hydraulic depending on loading, infill and size. The SAC and EHDC are also available as lift-out doors. The manual versions have a hold open safety stay, a heavy duty stainless steel slam latch (LO1), and are operated from above with a T key and can be operated from both sides. Locking options include the LO3 Tee Lock, a locking box, shoot bolts, a cam lock and a concealed deadlock.

On electric versions the actuators lock in position, with a control panel with 72 hour battery backup; the HIAC drawing shows two 24V actuators, with brackets that must be backed up to structure. The sheets give the opening angle: 85.0° on the HIAC, 86° on the SAC, 83° on the EHDC.

An open floor door is a hole. OSHA 29 CFR 1910.28(b)(3)(v) protects employees from falling through a hatchway by a hinged floor-hole cover and a fixed guardrail system that leaves only one exposed side, with the cover closed or a removable guardrail system on the exposed sides when the hole is not in use; by a removable guardrail system and toeboards on not more than two sides and a fixed guardrail system on all other exposed sides; or by a guardrail or travel restraint system when material passes through. Several sheets list a safety grid as an option. Whether a grid, a guardrail or both suits your opening is for your safety professional to decide against that paragraph.

Does it need a fire rating?

The HIAC and SAC sheets state that the doors are fire rated up to 4 hours to BS EN 1634-1: 2008 and BS EN 1363-1: 1999, and both say the door can be fire rated from the underside only. The EHDC sheet says it can be fire rated up to 4 hours and names no standard. None of the sheets names the performance criterion the hours refer to, so ask for the classification report, the fire direction and the tested size before you rely on a rating.

In the US, fire resistance is stated in hours. UL 263, Fire Tests of Building Construction and Materials, is a US fire test standard whose scope includes “composite slab and beam assemblies for floors and roofs.” Surespan’s evidence is a European test. Whether that is accepted for an opening in a rated floor is for the design team and the authority having jurisdiction. The same question for roof hatches is covered in Fire Rating Standards for Roof Hatches in the US.

Where noise matters, the HIAC, SAC and EHDC sheets give an acoustic rating up to 45dB.

Floor access door specification checklist

  1. Opening: structural opening, clear opening needed, overall frame from the sheet.
  2. Load: area load in kN/m² or psf, wheel load per wheel, point loads and their contact areas, and the maximum intended load for OSHA 1910.29(e).
  3. Lid: recessed with infill type and depth, flush plate, upstand, or internal.
  4. Finish: plate pattern, anti-slip coating or SureGrip.
  5. Water: self-draining with drain connection, or an upstand door.
  6. Operation and locking: manual, gas spring, electric, hydraulic or lift-out; lock type.
  7. Fire and acoustic evidence: rating, test standard, criterion, fire direction, tested size.
  8. Open-hole protection: guardrail or other protection under 1910.28(b)(3).

Frequently asked questions

Is a floor hatch the same as a floor access door?

Yes. Floor hatch, floor access door, floor door and floor access hatch are used for the same product: a framed, hinged or lift-out cover over an opening in a floor.

Can a floor access door take vehicle traffic?

Some can. The HIAC, SAC and EHDC sheets list wheel loads up to W8, 158 kN wheel load. The right class depends on the actual vehicle, its wheel loads and the door size, and the structural engineer confirms it.

Are Surespan floor doors H-20 rated?

The data sheets do not use H-20 or any US load standard. They give area loads and wheel loads in metric units. Do not treat any of them as an H-20 equivalent.

Is a flush floor door watertight?

Not the SAC or EHDC. Both sheets say the cover is not watertight and is self-draining, with a drainage channel to be connected to a drain by others.

What does OSHA require of a floor door?

For workplaces, 29 CFR 1910.29(e) requires each cover for a hole in a walking-working surface to support at least twice the maximum intended load and to be secured to prevent accidental displacement. Protection while the door is open is covered by 1910.28(b)(3)(v).

Drawings and data sheets are in the floor hatch resources. To discuss a specification, send the opening size, loads and finish through the Surespan contact page.

Sources

  • Surespan data sheet “Recessed Lid HIAC Floor Door”, revision mark REV 1.0 (04/21), file dated March 2022: type, recess, size, loads, operation, locks, fire, acoustic. Product page: Recessed Floor Hatch.
  • Surespan data sheet “Flush Lid SAC Floor Door”, revision mark REV 1.0 (07/22), July 2022: type, size, loads, drainage, operation, fire, acoustic. Product page: Flush Floor Hatch.
  • Surespan data sheet “Heavy Duty Floor Door EHDC”, revision mark REV 1.0 (07/22), July 2022: material, sizes, loads, drainage, operation, fire, acoustic. Product page: Heavy Duty Floor Hatch.
  • Surespan data sheet “Floor Access Hatch RSI Upstand Access Door”, revision mark REV 1.0 (07/22), July 2022: sizes, load, insulation. Product page: Upstand Floor Hatch.
  • Surespan data sheet “Floor Access Panel IAC Floor Door”, revision mark REV 1.0 (07/22), July 2022: type, frame, clearance. Product page: Internal Access Hatch.
  • OSHA 29 CFR 1910.29, paragraph (e), osha.gov.
  • OSHA 29 CFR 1910.28, paragraph (b)(3)(v), osha.gov.
  • UL 263, Fire Tests of Building Construction and Materials, Edition 14, shopulstandards.com.
  • FHWA, Comprehensive Truck Size and Weight Study, Volume 3, Chapter 6 (bridge design vehicles), fhwa.dot.gov.

Robert Fletcher

Rob leads Surespan’s global specification efforts, translating access requirements into permit-ready, code-compliant solutions across hatches, covers, ladders, vents, and skylights. He manages submittals and approvals to keep projects moving through permitting the first time.